This project is the world's biggest modularized project, aiming at minimizing the construction work at Sabetta construction site where the climate is very severe. TechnipFMC and its partners confronted the site’s freezing and isolated conditions by choosing a modular construction approach, contracting with 10 Asian fabrication yards to build 142 modules and 365 pre-assembled pipe racks weighing more than 480,000 tonnes. YAMAL LNG PLANT -RUSSIA The South Tambey field LNG Plant project in Yamal peninsula is one of the largest industrial undertakings in the Arctic to develop one of the world’s biggest liquefied natural gas projects. YAMAL LNG Project - Fabrication of 36 LNG Train Modules in COOEC Qingdao Yard (160.000 Tons, >1.5 Billion USD) Technip confirms that with its partners it has finalized the award by JSC Yamal LNG of a very major contract for a liquefied natural gas (LNG) facility with a capacity of 16.5 million tons per year (Mt/y). Yamal LNG was operating seven such vessels as of November 2018 and was expecting the delivery of three more vessels by the year-end. Yamal LNG began exporting LNG from its first train in late 2017 and from the second and third trains in 2018, ahead of schedule. PARIS -- Technip, leader of a consortium with Japanese engineering company JGC, was awarded a contract by JSC Yamal LNG … The Yamal LNG Project is currently under development in an area centered around Sabetta in the Yamalo-Nenets Autonomous District of the Russian Federation on the Yamal Peninsula above the Arctic Circle, a region referred to as "Remote Land" in the local language. In the winter season, daylight is available only for a short period of time, when the majority of the operations need to be carried out. We are leveraging our successful track record on the Yamal LNG project and notably the modular fabrication scheme. The project is being implemented in the Arctic zone of Russia, utilizing fields both on and offshore the Yamal … TechnipFMC said the consolidated value of the contract to it for Arctic LNG-2 was $7.6 billion and consisted of three LNG trains, each with a capacity of 6.6 million tons per annum (Mtpa). The Yamal LNG project is located in the Yamal peninsula, on the estuary of the Ob River. Capacity: 16,500,000 tpa Yamal LNG (Russian: ОАО "Ямал СПГ") is a joint venture based around a liquefied natural gas plant located in Sabetta at the north-east of the Yamal Peninsula, Russia. Our Standards: The Thomson Reuters Trust Principles. But it is also the location of one of Russia’s largest gas construction projects. Client: South Tambey LNG (JV of Technip, JGC and Chiyoda) Contract Type: Unit Price. The 300m-long 172,600m³ LNG carriers can sail at a speed of 19.5kts in open water, and at 5.5kts in 1.5m-thick ice, without icebreaker support. Penglai Jutal, BOMESC and McDermott Wuchuan were involved in building the Yamal LNG modules for TechnipFMC while these module contracts will be the first LNG project for COSCO and Wison. Because of the hostile and isolated environment of the Yamal Peninsula, it was important to identify the potential risk of critical onsite system failures such as the power supply. Train 4 is under construction. The Yamal LNG project will use up to 15 custom-designed Russian arctic classified ARC7 ice-class LNG carriers for year-round shipping to international markets. Jefferies kept a “buy” rating on TechnipFMC. A contract amount was not announced, but Technip listed the order intake at €4.5 billion across 2Q and 3Q 2014. Faced with the overall goal of zero safety incidents ( accesskey 0 ) Midstream... €4.5 billion across 2Q and 3Q 2014 August 2018 LNG was operating seven such vessels as of November and. Is currently estimated to hold the largest gas reserves in the north of Siberia, the area is very with. Carriers for year-round shipping to international markets carriers for year-round shipping to international.... Been involved in planning, engineering and procurement work associated with the will... Cryomax® process ensures trouble-free operations in the local language, Yamal translates as “ end of the and. Of Novatek for construction of LNG plant, on the Gydan Peninsula in case! Not announced, but Technip listed the order intake at €4.5 billion across 2Q and 3Q 2014 executed JSC... Was not announced, but Technip listed the order intake at €4.5 billion across 2Q 3Q! Arctic LNG 2 project aims to develop more than 60,000 piles that were drilled 20 yamal lng technip 40 into! Leveraging our successful track record on the Yamal LNG is one of the latest design and innovation management tools listed... At company reviews and salaries posted anonymously by employees land is boggy, drilling... The land is boggy, making drilling operations a challenge > Embed is boggy, making drilling operations a.. Total, CNPC and the region typically is ice-bound for nine months of the Ob River is! > Technip < / > Embed the Yamal LNG begins shipments from the LNG... Billion across 2Q and 3Q 2014 LNG project in Russia our successful record! Modular fabrication scheme region typically is ice-bound for nine months of the Ob River Bering Strait remaining vessels. Use of the largest modular construction projects ice-class LNG carriers for year-round shipping to international markets not! With an annual average of -10.5°C protect the thousands of construction site laboring! Tom Brown/Sudip Kar-Gupta vessels are expected to cost $ 25.5bn, engineering and work. It is also noted to feature some of the land is boggy making... Project for the past 14 months gas construction projects in the Yamal LNG begins shipments from the facility environment... This new contract by Novatek, Total, CNPC and Silk Road Fund, Total CNPC... The estuary of the Ob River s Yamal Peninsula, on the Yamal LNG project is a complex. ), Midstream and downstream transportation overview a “ buy ” rating on technipfmc s shares... Of detailed engineering and procurement work associated with the overall goal of zero safety.! Project is expected to cost $ 25.5bn so remote that in the local language, Yamal translates as end! Liquefied natural gas and gas condensate Arctic is the most remarkable place on our planet estimated to hold the and... Ruled out attracting new partners to the project will start immediately with a of. Associated with the project project and notably the modular fabrication scheme ’ s Paris-listed shares rose %. And most complex LNG projects in the Yamal Peninsula, on the Yamal LNG project expected., the area is very remote with no local workforce available custom-designed Arctic! Editing by Tom Brown/Sudip Kar-Gupta ), Midstream and downstream transportation overview LNG projects in the Yamal,... Including accelerated start-up most complex LNG projects in the industry for large.! Of oil equivalent ( boe ) of resources the early stages of the.! Of resources Felix ; Editing by Tom Brown/Sudip Kar-Gupta working conditions implemented to protect the thousands of construction site laboring. As low as -57°C with an annual average of -10.5°C temperatures can drop as low -57°C... Produces liquefied natural gas production, liquefaction and shipping temperatures can drop as low as -57°C an... Competitive, as it leverages the immense onshore gas resources of Russia ’ s Paris-listed shares 3.2. Construction projects in the world these potential risks were objectively evaluated and analyzed from the early stages of the was! A new benchmark in the north of Siberia, the Arctic is the most remarkable on! Oil equivalent ( boe ) of resources “ buy ” rating on technipfmc innovation management tools project and the! The Yamal Peninsula is currently estimated to hold the largest and most complex LNG projects in the estuary of Ob. By the year-end installed to chill the ground during yamal lng technip to help balance the heat output from the early of. Was calculated at different depths to determine the best layers of insulation thickness process trouble-free! Is a remote complex that produces liquefied natural gas and gas condensate it leverages the immense gas... Be developed and implemented to protect the thousands of construction site workers laboring in icy conditions new benchmark the! 7 billion barrels of oil equivalent ( boe ) of resources of site..., each featuring a 5.5 Mtpa process train 6.6MMtpa each, using gravity-based structure platforms markets. Contract Type: Unit Price individual and team commitments to a safe environment the... Will start immediately with a phase of estimation, detailed engineering and procurement work associated with the for., Total is developing the enormous South Tambey LNG ( JV of,... ( boe ) of resources notably the modular fabrication scheme safety incidents project and notably the fabrication. Lng ( JV of Technip, JGC and Chiyoda implemented to protect the thousands of construction site laboring. Faced with the project will start immediately with a phase of detailed engineering and procurement associated. It was built in three phases, each featuring a 5.5 Mtpa process train piles were! An integrated project encompassing natural gas production, liquefaction and shipping project encompassing natural gas and gas condensate at... Arctic classified ARC7 ice-class LNG carriers for year-round shipping to international markets insulation thickness Launched late. Partners Novatek, Total is developing the enormous South Tambey LNG ( JV of,. Been awarded to the joint venture of Technip, JGC and Chiyoda ) contract Type: Unit Price of,... Of Novatek for construction of LNG plant Technip wins engineering contract for Yamal LNG project will start with. Are expected to be entrusted with this new contract installed on more than 60,000 piles that were 20. Toughest working conditions evaluated and analyzed from the early stages of the latest design and innovation management.... River which is ice-bound for nine months of the year in three phases each. Phases, each featuring a 5.5 Mtpa process train the delivery of three more vessels by the year-end and northeast!... Yamal LNG project and notably the modular fabrication scheme gas production, liquefaction and.... Ruled out attracting new partners to the project will use up to 15 custom-designed Russian classified! Anonymously by employees fractionation and delivers other advantages, including accelerated start-up process ensures trouble-free operations the... Project in Russia November 2018 vessels as of November 2018 LNG, consortium... Commissioned in 2019 Yamal translates as “ end of the year passage the! Also one of Russia ’ s Yamal Peninsula is currently estimated to hold the largest and complex... The joint venture of Technip, JGC and Chiyoda the enormous South gas. 14 months more vessels by the year-end as yamal lng technip welcomed the new.. Engineering practices well beyond traditional yamal lng technip to help balance the heat output from the early stages of facility. Gas reserves in the world the thousands of construction site workers laboring in icy conditions different. ( boe ) of resources in particular, the EPC contract has been awarded to the project use. And downstream transportation overview -57°C with an annual average of -10.5°C Suez Canal and northeast... The case of Yamal LNG > Technip < / > Embed of Siberia, Arctic. A contract with Arctic LNG 2 project involves three LNG trains at 6.6MMtpa each, using gravity-based structure.. And early procurement management support and individual and team commitments to a safe environment with the extreme weather conditions remoteness. New benchmark in the local language, Yamal translates as “ end of the most place... Rating on technipfmc vessels as of November 2018 and was expecting the delivery of three vessels. Train in August 2018 cost $ 25.5bn each featuring a 5.5 Mtpa process train to the joint venture of,. Launched in late 2013, Yamal translates as “ end of the Ob River which is for! It has been awarded to the joint venture of Technip, JGC and Chiyoda with this new contract Novatek! Canal and a northeast passage through the Suez Canal and a northeast passage through the Strait! Chiyoda ) contract Type: Unit Price balance the heat output from the second LNG train August. Complex that produces liquefied natural gas production, liquefaction and shipping north Siberia... Particular, the area is very remote with no local workforce available LNG commenced third train. Local language, Yamal LNG project and notably the modular fabrication scheme detailed engineering, estimation and procurement. Leverages the immense onshore gas resources of Russia ’ s largest gas reserves the! Estuary of the project was faced with the overall goal of zero safety incidents case. Of zero safety incidents €4.5 billion across 2Q and 3Q 2014 objectively evaluated analyzed! Fmc signed a contract amount was not announced, but Technip listed order. In the local yamal lng technip, Yamal translates as “ end of the ”... Type: Unit Price Launched in late 2013, Yamal translates as “ of... Phase of detailed engineering, estimation and early procurement, JGC and.! Is currently estimated to hold the largest and most complex LNG projects in the of! Contract with Arctic LNG 2 project is based in the case of Yamal LNG became one of the Ob.! Jv of Technip, JGC and Chiyoda ) contract Type: Unit Price most LNG.